Every year, dozens of sewage overflows spilled into the
Roanoke River and its tributaries from adjoining sewer lines. And
millions of Roanoke taxpayer dollars went down the drain in attempts to fix
these problems. Between 1999 and 2003, cost overruns inflated sewage
project expenses from $73.5 million to $114.6 million.
On May 20, Blacksburg Town Council was presented with a
rush plan to make Blacksburg’s sewer system more like Roanoke’s. To fix an
impending capacity shortage in the North Main sector of Town, a sewer line
through the Toms Creek Basin (TCB) was proposed. It would cross Toms Creek
and tributaries 30 times, creating a 12.5-mile, 40-foot swath of destroyed
trees. Council was asked to approve either $11.2 million for this sewer
line or $5.9 million for North Main Street sewer repairs.
Town Staff pressed council to vote on this issue within
weeks because newly collected data showed that the North Main Street sewer
had reached full capacity flow. Staff did not explain, however, that these
full capacity data readings were enormous surges in flow over periods of
just a few hours caused by water leaking into sewer lines. These occurred
only during recent very heavy rains that broke all-time weather records.
During these same few-hour periods of rainfall,
millions of gallons of sewage overflowed in Christiansburg, Abington,
Wytheville, South Boston, Galax, and Roanoke. Every regional municipality
had massive sewage overflows except for Blacksburg.
No sewer line in
Blacksburg is thus facing imminent failure. A small future problem would
not be fixed, but grossly compounded by running a sewer through a creek and
floodplains that flood frequently, conditions that aggravate leakage due to
seasonal ground stresses on pipe connectors. This discredited engineering
practice would yield sewer line overflows, a polluted creek, sewage
treatment plan overflows and huge system upgrade costs in future decades,
just like in Roanoke.
The proposed TCB sewer line would also put an end to
Blacksburg’s low sewer bills, with a 52% 3-year sewer rate increase planned
to finance the proposed project.
With staff proposing only the worst possible
alternative to its pet TCB sewer line project, it was left to others to find
good options. A council member found a way to run a sewer line along the
U.S. 460 bypass to solve North Main’s long-term needs at a cost of $2 to $4
million. Municipal wastewater engineers told citizens of other inexpensive
options for the North Main problem, including equalization tanks and
non-intrusive measures for inflow reduction. And proven new technology
options such as one called “STEP” collection (see
www.tcbsewer.org for photos and description) could serve all development
through build-out in both North Main and the Toms Creek Basin.
STEP was among the wastewater systems recommended by
consensus as good options in 2001 by a Town-appointed expert working group
after a year-long study. Collectively called distributed sewer, these
systems are working reliably, economically, and aesthetically across the
nation. One in a dense Denver suburb serves 33,000 residents and
mega-shopping malls at a sewage treatment cost of $2.50 per home per month.
And a model such system installed in The Village at Toms Creek in Blacksburg
has been working successfully for two and a half years.
Developers should understand that distributed sewer is
sewer. Same service, no restrictions. A system with the size and
appearance of a shrub-lined tennis court, absolutely odor free, serves 100
homes. Unless you were a sewer expert, you would never know it was in the
community.
TCB sewer line
advocates are providing inaccurate information about these options. On June
3, for example, council was told of critically important land use figures
for distributed sewer systems that were too high by a factor of six.
The option of STEP collection for new development was ignored, and a
far-fetched plan for putting systems near existing pumping stations was
featured instead.
Let's not
rush, hope, and blunder our way into another sewer fiasco like Roanoke’s in
which Toms Creek, Heritage Park and the Toms Creek Basin are seriously
degraded and millions after millions of taxpayer dollars go down the drain